A specially trained technicians install the system in the existing facilities
Installation procedure
1. Remove insulation
2. Mark a line along the route of sensor laying, and remove rust preventive from the pipe
3. Lay strain and temperature compensation fiber
4. Repaint rust preventive
5. Reinstall insulation and restore
6. Start monitoring
*1 For the arrangement of one monitoring section, it takes for a maximum of 2 days. ( setting up scaffolding excluded . Several workings in parallel are practicable. )
Collect required data.
Input the optical fiber location into the analysis system and link it with measurements results.
PPP-BOTDA detection levels
Detectable strain change: ±5με
Detectable temperature change: ±0.25℃
Measurement speed: 5 s / 100 m